8/31/04 PROJECTED SHORTAGES OF FED FUNDS TO PAY ESI
MOPR Notes: Ref LEV20040921-5
where JZ mentions that this info was
prepared & handed out on 8/31 at a briefing for Jim Mitas & Loren Ellis
(both from Cgsm Akin's office). He continues thru section 10 of that
levee mtg to explain the 9/21/04 update; & in
section 13, DC stated that in the
wet early Spring, ESI didn't do very much work at
all; it was really slow; & he thought that in the month of
May, they only had about 4 or 5 days that they actually worked.
MERAMEC RIVER - VALLEY PARK, MISSOURI
FLOOD PROTECTION PROJECT
PROJECTED SHORTAGES OF FEDERAL FUNDS
TO PAY
ITEM IVB CONTRACTOR (ENVIRONMENTAL
SPECIALISTS, INC.)
FISCAL YEAR 2004 SITUATION
| Paid Contractor Earnings thru April
2004 |
$1,300,000.00 |
| |
|
| Actual Unpaid Contractor Earnings |
|
| Apr 2004 |
597,515.85 |
| May 2004 |
537,053.36 |
| Jun 2004 |
949,680.82 |
| Jul 2004 |
1,699,483.22 |
| |
|
| Projected Unpaid Contractor Earnings |
|
| Aug 2004 |
1,500,000.00 |
| Sep 2004 |
1,300,000.00 |
| |
|
| Total Actual & Projected Unpaid
Earnings in FY 04 |
$6,583,733.25 |
| Approximate interest earned by
contractor in FY 04 |
30,000.00 |
| Total approximate debt to contractor
in FY 04 |
6,613,733.00 |
| Round to |
$6,600,000.00 |
| |
|
| |
|
| |
|
| Additional Federal funds needed in
FY 04 = approximately |
$6,300,000.00 |
| Additional sponsor cash contributions
when Fed $ arrive, approx |
300,000.00 |
| |
|
| |
|
| FISCAL YEAR 2005 SITUATION |
|
| |
|
| President's Budget |
$2,060,000.00 |
| Approximate Fed amount that will be
paid to contractor
|
1,000,000.00 |
| |
|
| |
|
| Contractor will complete the job, &
will have earned |
|
| the total contract amount plus
interest, say..... |
$14,800,000.00 |
| |
|
| |
|
| Contractor will have been paid about |
2,300,000.00 |
| |
|
| |
|
| Contractor will be owed about |
$12,500,000.00 |
| |
| |
|
|
|