11/21/05
LEVEE PUNCH LIST
MOPR Notes: Ref
LEV20051121 where DC explains this,
his written list of items to be resolved before VP gets finalization on the
levee. Three X's (XXX)
below identify Items that he had lined out.
|
PUNCH LIST FOR ITEM IV-B: Fishpot Structure -
JB-1 Area
|
| 1.
|
Steel pipes filled with concrete
(bollards) need to be placed on the north side of junction box to
prevent any vehicles from jumping curbs & hitting operators & junction
box. # & location of bollards to be determined in field. |
| 2. XXX |
One section of fiberglass grating on the
south side of structure is wobbly. Concrete needs to be ground off
level so grating sits flat on top of junction box. |
| 3. XXX |
Arrows need to be placed on operators to
indicate direction to "Open" or "Close" sluice gate (see
Part 2.5.7 Page 15100-7) |
| 4. XXX |
Anchor bolt nuts should be bronze (see
Part 2.5.7 Page 15100-7) |
| 5. XXX |
Repair erosion & washout areas. |
| 6. XXX |
Reseed, mulch & fertilize as required. |
|
Page 1 |
|
PUNCH LIST FOR ITEM IV-B: Fishpot Outlet FES-1
Area
|
|
1.
|
Repair erosion & washout areas. |
|
2.
|
Reseed, mulch & fertilize as required. |
|
3.
|
Why does back of pkg lot drain down the
slope to det pond instead of to grated inlet in pkg lot or to grated
inlet at the northwest crown of det pond? |
|
Page 2 |
|
PUNCH LIST FOR ITEM IV-B: Route 141 Gatewell &
Outlet - GW1
|
|
1. XXX |
Anchor bolt
nut should be bronze (see Part 2.5.7 Page 15100-7) |
| 2.
XXX |
Arrows need to be placed on
operator to indicate direction to "Open" or "Close" sluice gate (see
Part 2.5.7 Page 15100-7) |
| 3.
|
Gravel road on crown of levee
needs to be extended from the emerg road to beyond 141 Gatewell.
(so the emerg equipmt vehicle has access to gatewell operator) |
| 4.
|
Telephone & cable lines need
to be raised. |
| 5.
XXX |
Emerg road gate needs to ((be))
relocated to allow fire truck to make turn onto emerg road from
MerStaRd. Distance between gate post needs to be A
{sic} wider.
(locations & distances to be determined in field) (Ramp Road A) |
| 6.
XXX |
Sheet pile to be cut off &
fill placed. |
| 7.
|
Repair erosion & washout
areas. |
| 8.
|
Reseed, mulch & fertilize as
required. |
|
Page 3 |
|
PUNCH LIST FOR ITEM IV-B: Detention Area A
((AL-Arnold's Landing))
|
|
1.
|
Inspect &
clean outlet into det area. |
|
2.
|
Clean silt &
debris at headwall. |
|
3.
|
Backfill &
replace riprap around head wall. |
|
4.
|
Repair erosion
& washout areas. |
|
5.
|
Reseed, mulch
& fertilize as required. |
|
Page 4 |
|
PUNCH LIST FOR ITEM IV-B: Meramec Valley Plaza
((MerVPlz))
|
|
1.
|
Pkg on gravel area between flood wall &
blacktop. Some type of barrier needs to be installed to prevent
damage to flood wall if used for pkg & storage of vehicles. |
|
2.
|
Loana to place invert at SRI-B. |
|
3.
|
Loana to have AmerenUE repair guy wire at
EXI-A. |
|
4.
|
((blank)) |
|
Page 5 |
|
PUNCH LIST FOR ITEM IV-B: Detention Area B
|
|
1.
|
A storm water pipe needs to be installed
under Ramp Road B to drain the area between the BNSF RR Right Way & Ramp Road
B & the landside of levee slope southwest of Ramp Road B into SAI-B. |
| 2.
|
Repair erosion
& washout areas. |
| 3.
|
Reseed, mulch
& fertilize as required. |
| 4.
|
City to investigate storm water drain
east side of 3rd St & advise COE. |
| 5.
|
Storm water pipe between EXI-B & FES on
the east side of the Ramp Road B needs to be changed so this pipe will
drain properly. |
|
Page 6 |
|
PUNCH LIST FOR ITEM IV-B: 3rd St Sluice Gate
|
|
1. XXX
|
Anchor bolt
nut should be bronze (see Part 2.5.7 Page 15100-7) |
| 2.
XXX
|
Arrows need to be placed on
operator to indicate direction to "Open" or "Close" sluice gate (see
part 2.5.7 Page 15100-7) |
| 3.
|
Repair erosion
& washout areas. |
| 4.
|
Reseed, mulch
& fertilize as required. |
|
Page 7 |
|
PUNCH LIST FOR ITEM IV-B: 5th St Gravity Drain
|
|
1. XXX |
Anchor bolt
nuts should be bronze (see Part 2.5.7 Page 15100-7) |
| 2.
XXX |
Arrows need to be placed on
operators to indicate direction to "Open" or "Close" sluice gate (see
Part 2.5.7 Page 15100-7) |
| 3.
|
COE to investigate the EPA Region 7 &
MDNR remedy for the VP TCE Site, Operable Unit 2 (OU2) in VP, MO & its
effect on storage of the add'l water into the det area C during a flood
event. |
|
Page 8 |
|
PUNCH LIST FOR ITEM IV-B: Detention Area C
|
|
1.
|
Repair erosion & washout areas. |
|
2.
|
Reseed, mulch & fertilize as required. |
|
3. |
Work on addition of storm water drain
betwen SA-1-4 & SA-1-5 (see drwg. {sic}
7/C-21 & 7/C-22) Needs to be completed (mod already approved) |
|
Page 9 |
|
PUNCH LIST FOR ITEM IV-B: Misc on Item
IV-B
|
| 1.
|
Clean River Dr from Ramp Road A (west of
Hwy 141) to Ramp Road B (east of BNSF RR Bridge (( )
)) & Repair. |
| 2.
|
Perman((en))tly block River Dr on east side of
Ramp Road B. |
| 3.
|
Clean & repair River Dr from Kena Ave
west to the west entrance of the Boat Ramp Pkg Lot. |
| 4.
|
Erosion on river & land sides of levee
needs to be repaired, reseeded, mulched & fertilized as required. |
| 5.
|
Natural gas line over levee at Pharoah
Ave needs to be inspected by COE & approved that it meets all requiremts
of specs. |
| 6. XXX |
Security gate on River Dr west of Kena
Ave to be moved & installed at the sourth end of Pharoah Ave (City VP
will relocate gate if COE approves) |
| 6.
|
Silt fences need to be repaired on river
& land-side of levee. |
|
Page 10 |
|
PUNCH LIST ITEM For St Louis Ave Closure Structure
|
| |
Sill plate across St L Ave is loose.
Dwayne Actkley ((should be Duane Atchley))
COE Structural Eng has worked up a plan to repair this
problem. (COE responsible for repair)
|
|
PUNCH LIST ITEMS For III-B: Grand
Glaize Creek
((GG Creek))
|
| 1. |
Storm water pipe on north side of Leonard
Pk at toe of land-side levee continues to wash out (city has filled
washouts a couple times). COE rep inspected inlets & pipe joints &
suggest to city worker & myself a way to test for leakage. City
workers tested pipe & inlets & found sufficient signs of leakage & needs
extensive work to repair. (City is obtaining a cost est to make
repairs. If city makes these repairs they will expect credit from
their share.) |
| 2. |
Fiberglass grating on junction box at the
GG Det Pond & inlet to sluice gate is to((o)) weak an((d)) needs to
((be)) replaced with galvanized steel grating. (City has placed
steel plates over grating to prevent someone from falling into junction
box structure.) |
|
Page 11
|
|
PUNCH LIST ITEMS For III-B: Grand
Glaize Creek
((GG Creek)) ((Cont'd))
|
| 3. |
Dike between north side of the creek
channel & south side of wetland pool continues to erode away. COE
has repaired the dike on the north side of the creek channel. Some
of this repair looks good but there is a large section that is severely
eroding. COE needs to inspect the damage & access if dike washes
out will it cause damage to creek-side of levee.
(({sic} sentence structure)) |
|
PUNCH LIST For ITEM II: Fishpot Creek
|
| 1. |
Sill plate across Vance Rd is loose.
Dwayne Actkley ((should be Duane Atchley))
COE Structural Eng has worked up a plan to repair this
problem. (COE responsible for repair) |
| 2. |
The sluice gate operator needs a new stem
cover (Cover has been replaced twice. Vandals have removed it.)
Can city crew make new one? (may not match original) |
|
Page 12
|
|